Hi, guys,I have met a problem.

I just final confirmed the PM01 order in the SAP. but unfortunately, I incorrectly input the actual work time by mistake (it should be "30min", but i had input "60min"). 

So now, I would like to know, if it is possible to change the actual work time for this final confirmed (completed) order? How can i change it ?

Great thanks for your help in advance!

Comments

In case the order is closed then, go to the procurement departement and let them reopen the order.
By: | 22 Oct 2009
You can cancel the confirmation in IW45 & post another confirmation thru IW41 again with new values.
If the order is already closed you can reopen the order thru IW32.
By: | 22 Oct 2009