Hi ,

Requirement : Even for LTP run system should consider the Sloc MRP indicator.

It is the standard SAP feature to consider the Plant Stock during the LTP (Simulation Run) though a particular storage location is excluded from MRP.
The Sloc MRP indicator set for a storage location of a material is considered in operative planning and not in LTPas per the SAP Note : 208017 .

Can anyone give me a workaround  solution to exclude the SLoc MRP indicator for LTP run also.

Awaiting for your valuable inputs.

Regards
radhak mk