LTP run should consider the Sloc MRP indictor rather than complet Plnt Stk.
Hi ,
Requirement : Even for LTP run system should consider the Sloc MRP indicator.
It is the standard SAP feature to consider the Plant Stock during the LTP (Simulation Run) though a particular storage location is excluded from MRP.
The Sloc MRP indicator set for a storage location of a material is considered in operative planning and not in LTPas per the SAP Note : 208017 .
Can anyone give me a workaround solution to exclude the SLoc MRP indicator for LTP run also.
Awaiting for your valuable inputs.
Regards
radhak mk